The BCIS Online featured project for June 2018, submitted by the Department of Health & Social Care, is the recently completed £17million Children's, Young People and Perinatal Mothers’ Hub in Woodthorpe, Nottingham.

The hub offers specialist inpatient care and support for adolescents and perinatal women experiencing acute mental health difficulties that can no longer be managed in the community. It is also the base for the Trust’s Community Child and Adolescent Mental Health Services.

The campus-style mental health care hub is arranged over 3Nr detached, irregular shaped on plan buildings, comprising:

  • two storeys, 2,985m2 adolescent unit with 2Nr enclosed courtyards, providing 32Nr inpatient ensuite beds, which includes a 12Nr bed general adolescent unit, 12Nr bed eating disorders ward and 8Nr bed psychiatric intensive care unit
  • two storeys, 999m2 8Nr ensuite bed perinatal unit, including consultation rooms, providing support for mothers with serious mental health issues before and after having a baby
  • two storeys, 1,270m2 education and community centre with an enclosed courtyard, providing classrooms including specialist teaching areas, therapy rooms and clinic.

The combined building cost is £2,683/m2 (3Q2016). The functional unit rate equates to £352,469 per bed space.

Elemental breakdown

Substructure, at £408/m2 includes:

  • RC strip foundations and ground slab.

Superstructure, at £918/m2 includes:

  • steel framing
  • concrete on metal sheet upper floors
  • Kingspan metal clad pitched and flat roofs
  • combination of facing brick, rendered block, laminate cladding, aluminium and glazed curtain walling
  • metal stud partitions
  • timber doors.

Finishes, at £218/m2 include:

  • plasterboard, skim, tiled and sheet wall finishes
  • carpet and vinyl sheet floor finishes
  • plasterboard suspended ceilings.

Fittings and furnishings, at £127/m2 include:

  • cupboards, worktops, signs and mirrors.

Services, at £1012/m2 include:

  • sanitary ware
  • gas boiler LTHW heating and air conditioning
  • passenger lifts
  • fire, intruder and staff attack alarms, video/audio door entry systems, disabled refuge, induction loops, CCTV and data.

The £/m2 figures include preliminaries, at 16% of the remainder of the contract sum excluding contingences, apportioned by cost.

The project was procured using the NEC3 target cost contract, with a construction period of 156 weeks.

BCIS would like to thank DHSC for providing the data and everyone who submits projects to be published online.

Cost analyses are available as part of the BCIS Online service.

BCIS Online is an industry repository for building project costs analysed elementally. It provides clients, consultants and contractors secure online access to their project data. The analyses can be prepared from contract documents used in most procurement routes, for example:

Procurement route Required Needed Optional
Design and Build Contract Sum Analysis Employers' Requirements or Contractors' Proposals Drawings
Specification and Drawings Contract Sum Analysis Specification Drawings
Traditional BQ   Drawings
Target Cost Target Cost Breakdown Specification Drawings
All projects require gross internal floor area, date on which the costs were agreed and location if not included in the supplied documents.

If you would like to talk to BCIS about analysing your project data, please contact Metin Mustafa on +44 (0)20 7695 1518 or email the BCIS data team.